North Tipperary County Council has announced construction on the Thurles Regional Water Supply Scheme has started.
The construction of the €10 million Thurles RWSS Contract No 1 has commenced. The contractor for the scheme is Regan Civil Engineering. The works under Contract No 1 consist of 41km of trunk and distribution water mains and a 10,000 cu.m reservoir. The current area of work is off-road at Raheen & Farneybridge, Holycross. The Contractor has applied for a road closure of the L-4123 at Bohernacrusha to Raheen from the 20thAugust to 12th October.
Contract No 2 is estimated at €16 million and includes the construction of the Water Treatment Plant by DBO.
Contract No 2 is due to start in early 2013.
(CD/GK)