A £107,000 resurfacing project is to begin on a section of Finaghy Road South in Belfast.
The scheme, due to start on Monday 20 April, is to improve the footway and carriageway surfaces. The work is expected to be completed in four weeks.
The off-peak lane closures will continue for approximately three weeks. During the off-peak lane closures, two-way traffic flow will be maintained.
To enable the final surface to be laid, full road closures will be required on Sunday 10 May and Sunday 17 May from 7am to 8pm. Signed diversionary routes will be in operation.
(CD/JP)