Construction work is to begin on a £200,000 road resurfacing project in Ballyclare, Co Antrim.
The work is to take place on the Rashee Road between Cogry Road and Readers Park. It is scheduled to begin on Monday, 26 February, and will be completed by Monday, 23 April.
Most of the work will be carried out using a one-way closure, with Ballyclare bound traffic diverted along the Trenchill Road and Ballyeaston Road. Doagh bound traffic will use the Cogry Road, Bridge Road, Mill Road and Station Road. All diversions will be clearly signposted and to help minimise inconvenience to the travelling public and local businesses, the majority of the work will be completed off peak.
A full road closure is necessary to lay the final road surface and this work will be carried out during weekends to reduce the impact. At this stage, this is planned to take place from 6am on Saturday, 24 March until 6am Monday, 26 March, and from 6am on Saturday, 14 April until 6am on Monday, 16 April.
Diversions will be put in place.