Work on the first section of a 3.5km watermain between Ally Hill Service Reservoir (SR), on the outskirts of Lough Bradan and Doochrock SR near Ederney in Fermanagh, has been completed.
NI Water has invested £1 million in the project and the new upsized watermain will replace the old cast iron pipe which runs through Lough Bradan Forest and along Glen Road and Mweelbane Road.
Work on the roads is due to get underway followed by a final short section in the forest in May.
NI Water's contractor, BSG Civil Engineering will need to implement temporary road closures during the work.
Martin Gillen, NI Water Project Manager, said: "This larger diameter watermain is being laid to provide a more robust means of transporting water from Lough Bradan Water Treatment Works to a number of storage reservoirs in the area, including Doochrock, Drumkeeran, Largy and Drumharvey, which in turn supply much of the North/North West and East of Fermanagh.
"Unfortunately due to the narrowness of local roads, it will be necessary for our contractor to implement short road closures to ensure the highest levels of health and safety for both workers and the general public.
"The first section of road affected by pipelaying will be part of the Glen Road – from 143 Glen Road to its junction with Mweelbane Road – which will be closed to through traffic from Monday 9th April until Friday 4th May. The Mweelbane Road will then be closed from its junction with the Glen Road up to 161 Mweelbane Road from Monday 7th May for a week to facilitate pipelaying. Advance notification of the work will be erected in the area and letters will be delivered to residents living on these roads for whom access will be maintained at all times. We would kindly ask all other motorists to follow the diversions signposted."
(CD/MH)