Construction Ireland Construction Directory
Time and date
CONSTRUCTION DIRECTORY
Share this page
Construction News
11/07/2022

Milestone Reached On Translink's Antrim Railway Overbridge

Construction News Image
Work on Translink's new railway overbridge outside Ballymoney has reached a major project milestone.

FP McCann successfully completed the installation of the 15.2m long precast concrete pre-stressed bridge beams on the over bridge.

This work forms part of the XL 122 to 126 User Worked Crossing Closure Project.

The 15.2m long bridge beams supplied by Banagher Precast Concrete were installed within an eight-hour railway line possession utilising a Liebherr LTM 1220-5.1 mobile crane supplied by the Tusker Construction Group working at a 22m slewing radius with maximum beam weights of 22.42T. In addition to the bridge beam installation, a proprietary 'Ultraguard' guardrail system was also installed during the rail possession to the bridge edge beams to allow the remaining bridge construction works to be completed during normal working hours and train movements. In preparation for the bridge beam installation, FP McCann employed Design ID to undertake and complete a Category 3 Temporary Works Crane platform design to NR/L2/CIV/003, which following Translink approval was then constructed adjacent to the bridge structure. Just in time delivery was utilised to avoid site congestion or affect local residents or road users. The Bridge beams were therefore delivered direct to site from the Banagher manufacturing facility in Co. Offaly on the night of installation. For the safe access and egress to the site by the heavy haulage company delivering the beams on extended length trombone trailers, a lane closure on the Ballybrakes Road as pre-agreed with DfI Roads Service was installed and managed throughout the night by FP McCann Traffic Management Operatives.

-- Advertisement --

Following the last update on the XL 122 to 126 User Worked Crossing Closure Project in March 2022, as well as achieving the major milestone of installing the bridge beams over the railway, FP McCann has completed construction of 2no. 'MacWall – Vertica' Earth Retaining Structures either side of the rail line to support the new bridge access ramps.

The Earth Retaining Wall was designed by Maccaferri on behalf of FP McCann and consisted of 3260no. Macwall – Vertica 4 degree concrete facing blocks, and 2360m2 of Paragrid 50/15 geogrid reinforcement supplied by Maccaferri with 4800t of Class 6I granular fill imported by FP McCann from its Bradley's Quarry, located in nearby Kilrea. The walls were constructed 4.5m from the live running railway (which remained fully operational throughout the construction of the walls) to an average height from running rail of approximately 5.5m. The walls were constructed in layers dictated by the wall design, with the granular Class 6I backfill material (once compacted in accordance with the MCHW) then stabilised through the introduction of paragrid reinforcement layers behind the concrete block facing units. The design theory of the wall being that the larger the stabilised earth/granular material mass, the more material can be retained or held back. The geosynthetic reinforcement layers extend past the theoretical failure plane and serves to create a large, rectangular mass of block and earth/granular material, restraining the retained embankments. Both walls were constructed within a five-week period.

Latest Construction News

01/05/2024

Sisk has been named as the main contractor for the first two phases of Vantage Data Centres flagship Ireland campus (DUB1) at Profile Park in Dublin. Located across 22 acres, the initial stages of the campus will include a 32MW facility and a 20MW facility, with the first phase set to be in ...
01/05/2024

NI Water has become one of the first public sector organisations to install a battery energy storage system which will reduce its carbon footprint. The 4.1 MW battery is powered by an existing solar farm at one of NI Water's largest water treatment plants at Dunore Point in Antrim. The battery has ...
01/05/2024

Kildare County Council has marked the completion of a new development of ten housing units at Ard Sceach, Coill Dubh. The units which were under 'Housing for All – a New Housing Plan for Ireland', includes four 1-bedroom properties as well three two-bedroom properties and three-bedroom houses. The ...
01/05/2024

The Government has updated and launched the Project Ireland 2040 Progress Tracker and the 'MyProjectIreland' interactive map. Project Ireland 2040 includes a transparent long-term strategy for public capital projects out to 2040. The 10-year period out to 2030 is backed by funding of €165 billion ...
01/05/2024

Infrastructure Minister, John O'Dowd has announced that the resurfacing and widening scheme on the A3 Portadown Road in Armagh has been completed. The scheme which extended for 1.3 kilometres will improve the structural integrity and surface quality of this busy A class road. Announcing ...
01/05/2024

Mid and East Antrim Borough Council has hosted the latest Industrial Decarbonisation for Northern Ireland (IDNI) workshop which was attended by over 20 local businesses. Under the guidance of Invest NI, the event aimed to educate businesses and stakeholders about the objectives of IDNI, an ...
01/05/2024

Gas Networks Ireland has launched its new pre-excavation safety campaign with the introduction of its new campaign 'ambadgador', known as Keith. The campaign highlights the importance of safety first, urging individuals to always check for gas pipelines before they break ground. Gas Networks ...
01/05/2024

Cork County Council has officially launched its Town Centre First (TCF) Regeneration Plan for Skibbereen. The ambitious yet practical plans for Skibbereen Town Centre represents the culmination of extensive public engagement led by Cork County Council, aligning with the nationwide Town Centre ...
01/05/2024

The Housing Executive has announced that progress has been made to transform land in Laurencetown into a community garden and allotment with the introduction of a new shed and gardening tools. The Laurencetown Lenaderg and Tullylish Community Association received a £2,600 Community Grant, which ...
01/05/2024

SSE Renewables has announced that it will be the principal sponsor of the Irish National Sheep Dog Trials which are taking place this August in County Donegal. Organised by a voluntary Donegal Committee comprised of members of the International Sheep Dog Society, the trials are being held in ...
MCR GroupDC Heat Pump ServicesTower Gardening & Tree ServicesReisser IrelandSanctuarysynthetics at GrasslandAdonis Safety TrainingSpratt Fireplaces & Stoves Centre LtdFernhill StoneVision Creative StudiosBathroom Store Online
Terms and Conditions
2024/05/02 04:24:27