The £200 million Belfast Transport Hub Project is continuing to make significant progress.
FK Lowry marked a key milestone on the project as the firm installed the final pile on site.
The project is a joint venture of Farrans and Sacyr and they have been appointed to deliver the main works for the £200m major transport hub in Belfast City Centre.
The project will include the construction of 26 new bus stands and eight railway platforms on the site of the old Great Victoria Street Station.
FK Lowry was contracted to design and install 1,700 CFA Bearing Piles using two Soilmec SR-75 and SF-65 Piling Rigs. FK Lowry delivered the project safely and to programme and budget.