13/04/2023

Development Of West Cork Pipeline Reaches Key Milestone

Construction News Image
The construction of a brand new pipeline from Bandon to Clonakilty in West Cork is continuing to make significant progress.

Led by Uisce Éireann, the project for 13.5km of new water mains is now over the halfway mark.

The works involve the construction of trunk water mains connecting Bandon Water Treatment Plant (WTP) on Carhue Hill to the WTP at Jones' Bridge in Clonakilty via Baxter's Bridge and the N71. 

Lisa Cogan, Uisce Éireann Regional Delivery Lead said: "We are delighted to be over the halfway mark with approximately 10km of watermains constructed. This vital project will support growth and development in the beautiful West Cork town of Clonakilty and will ease the current supply challenges in the area.

-- Advertisement --

"We have been hard at work along the N71 and are progressing through the project on schedule, working in partnership with, Cork County Council and Ward and Burke Construction Ltd. I would like to thank the people of West Cork for their patience and co-operation during the works.

"Uisce Éireann is committed to playing its part in the national drive to provide homes to people who need them by developing and prioritising the delivery of key water services infrastructure."

The capacity of treated water available at Bandon WTP means additional supply can be delivered to Clonakilty, while continuing to supply Bandon; all without taking additional water from the Bandon River. As a result, both areas will be able to continue to facilitate social and economic growth. 

For Clonakilty, the additional supply provided by this project will allow for housing to be developed in the short to medium term while also playing an important role in the long-term solution for the town and the surrounding areas. 

Uisce Éireann will continue to carry out the works on the N71 Bandon to Clonakilty Road which are anticipated to be completed in early June. From there, a further 2.4km of water mains will be constructed on local roads. The works, being carried out by Ward and Burke Constructions Ltd, are expected to be completed by Autumn 2023.

Latest Construction News

03/05/2024

Construction work has commenced on a new £9 million build at Rowandale Integrated Primary School in Moira. Funding from the Fresh Start Programme will facilitate the establishment of a new, modern primary school, with 14 classrooms and a nursery unit capable of accommodating over 340 ...
03/05/2024

Minister for Agriculture, Food and the Marine, Charlie McConalogue T.D. together with Leas Chathaoirleach of Donegal County Council, Cllr Gerry McMonagle, has opened the Greencastle Harbour Breakwater. The 270-metre Breakwater aims to improve the protection of vessels in the harbour against wave ...
03/05/2024

NI Water has initiated a £3.5 million improvement programme at Newcastle Wastewater Treatment Works (WwTW). Murphy Dawson Wam JV is undertaking the project, which focuses on improving the three-stage treatment process at the current facility. This will entail installing new filtration gear and a ...
03/05/2024

Bennett Construction has announced that it has achieved Practical Completion (PC) on the Tristan Square Development in Chapelizod, Dublin. The project includes the construction of 180 social and affordable apartments split in to one, two and three bed homes over three blocks. Each of the units are ...
03/05/2024

SSE Renewables and FuturEnergy Ireland have revealed that Microsoft has committed to a lengthy Corporate Power Purchase Agreement (CPPA) with the co-developers. This agreement will inject 30MW of wind energy into Ireland's power grid through the recently launched Lenalea Wind Farm, located near ...
03/05/2024

Farrans has announced that it has collected three awards, including one Gold, at the Considerate Constructor Scheme's National Awards. The CCS National Awards honour outstanding sites, organisations and people who show exceptional commitment to the Code of Considerate Practice in Community, ...
03/05/2024

County Down headquartered GRAHAM has started construction work on a new £59 million low-carbon development in Edinburgh. The Burnet Point scheme in Abbey Lane which combines student flats, build-to-rent and affordable homes is the first-ever mixed-use residential development of its kind by Unite ...
03/05/2024

Alliance's Housing spokesperson, Kellie Armstrong MLA, has welcomed the NI Federation of Housing Associations (NIFHA) commitment to reduce carbon emissions in social homes and combat climate change. Housing associations are currently in the process of developing a scheme set to launch this autumn. ...
03/05/2024

Fibrus has announced that it has exceeded its 80,000 customer milestone, as it gains over 50,000 customers in just one year. The broadband provider burst on to the scene to transform the digital infrastructure of rural and regional areas of Northern Ireland and has shaken up the market due to its ...
03/05/2024

Infrastructure Minister, John O'Dowd, has announced his support for the 'No Mow May' approach to help promote biodiversity on the roadside during this month. The Department for Infrastructure oversees the maintenance of 45,000km of grass verges along the road network. In recent years, it has been ...