Subscribe to our Construction Newsfeed
Ireland Construction Directory
Search our 25,487 companies....

Construction News

18/09/2024

Unique Solution For Limerick Hospital Excavation

Groundforce equipment has played a crucial role in the construction of a new extension to University Hospital, Limerick, in Ireland.

The new 9,800m2 acute ward, is built over the existing emergency department and dialysis unit and consists of 96 ensuite single rooms over four floors.

As part of the project, main contractor Sisk was required to build a new lift core, adjoining the existing hospital building and lower-level car park, to service the new structure.

The lift core rises from an 8m-deep excavation dug immediately adjacent to the existing building. The bottom 4m of this excavation was in the bedrock, comprising a hard granite material, and was self-supporting. The upper 4m was in the overlying soil and required temporary support to prevent any collapse.

This was the element of the project that required the services of Groundforce.

"The excavation needed temporary support on three sides - the fourth side was the wall of the existing hospital building," explained Groundforce director Joseph Lenihan.

The usual method employed by Groundforce is to support the sheet-piled retaining walls with modular extendable waling beams around the perimeter and hydraulic props spanning the excavation from side to side and bearing on the waling beams.

However, the size of this excavation (measuring approximately 14m x 17.5m) and its location against the wall of an existing building required a different approach.

"It was acceptable to the client for the adjoining wall to take a shear load from the shoring system but not a point load," said Joseph Lenihan, "Therefore the shoring system had to rely on lateral restraint from the adjacent ground."

-- Advertisement --

The shoring system comprised two levels of Mega Brace frame supporting the 5m-long Larssen L603 sheet piles lining the excavation and four of Groundforce's MP150 modular hydraulic props installed as corner struts at the end of the excavation furthest from the hospital building.

Groundforce also supplied the MS4 piling hammer to install the sheet-piles. Perimeter safety was provided in the form of Groundforce's Edgesafe barrier and davit-arm rescue system.

The lateral loads from the three braced sides of the excavation were transferred along the line of the sheet-piled retaining walls which, together with the earth behind them, provided a shear key to prevent any point load transferring to the adjacent building.

The shoring system design was developed jointly by Groundforce and Sisk's temporary works department and approved by the project's consulting engineer, Arup.

"During the design stage a concern was raised by the Sisk design team regarding the transfer of the load to the shear key," said Joseph Lenihan. "A typical hydraulic bracing system is pressurised to prevent any lateral movement. However, this lack of movement would not allow the shear key to take effect - the adjacent ground would not be given the chance to take the load.

"The solution was to not lock-off the ram element of the frame, thereby allowing it to contract once the system became loaded. This allowed a certain amount of movement and ensured that no point load was transferred to the adjacent wall.

"It's fair to say that we've never done this before," he added.

The unique requirements of this operation demanded close collaboration between designers from Groundforce and Sisk's temporary works department.

"There was a lot of design development required, not just for the shoring system itself but for the sequence of its installation and removal," said Sisk's project manager Stephen Geraghty.

"In fact, almost as much design went into the removal of the temporary works as for the installation. The sequence of backfilling to a certain level, concreting and removing the bracing had to be carefully planned."

Carrying out the work so close to the existing building brought the added risk of disturbance to the hospital's staff and patients. Noise and vibration therefore had to be kept to the absolute minimum and was carefully monitored.

"When it came to excavating through the rock we had to bring in a specialist to drill it out in small sections instead of going in there with heavy machinery. The excavation was quite slow: the first two or three weeks were spent just drilling/hydraulic breaking rock," said Stephen Geraghty.

During the works, weekly design workshops ensured that the temporary works element remained under scrutiny.

"It was certainly tricky. But we kept in constant dialogue with Groundforce and I can't complement them enough," he added.

Latest Construction News

19/10/2026
PJ Hegarty has been named winner of the Supreme Safety Award — the top accolade at the All-Ireland Occupational Safety Awards — and also picked up the Healthy Workplace Award and the Consistent High Achiever Award. The trio of honours was announced at a gala at the Great Southern Killarney. Organis
Read More
19/10/2026
AG, the third-generation paving and building products manufacturer with more than 60 years' experience, has expanded its partnership with GRAHAM via a new Strategic Supply Agreement that appoints AG as a preferred supplier until the end of 2028. GRAHAM, which traces its heritage back over 250 years
Read More
19/10/2026
Households exporting surplus electricity to the grid will be able to keep more of what they earn, a Fine Gael TD has said, a change he believes will encourage more homes to install solar panels. Deputy Naoise Ó Muirí, chair of the Oireachtas Climate, Environment and Energy Committee, said lifting t
Read More
19/10/2026
A major water infrastructure scheme to enable future housing in Sligo Town is set to begin in Summerhill this month, Uisce Éireann has announced. The investment will expand capacity in the local water network, supporting new homes and sustainable growth in one of the town’s key development zones.
Read More
19/10/2026
Planning permission has been approved for the Sunflower Children's Hospice in Castlebar, a major step forward for specialist paediatric palliative care in Ireland. The facility will be the first children's hospice built outside Dublin and the first new children's hospice to be developed in the count
Read More
19/10/2026
Coillte, working with Leitrim County Council, has begun development works at Glenfarne Wood in Co Leitrim, launching a first-phase investment of €2.7 milliom. The programme is backed by €2.5m in funding from the Department of Rural and Community Development and the Gaeltacht and is part of a two-p
Read More
19/10/2026
Armagh City, Banbridge and Craigavon Borough Council and Ulster Wildlife hosted Finance Minister John O'Dowd at Peatlands Park to signal the commencement of the PEAT+ initiative, a €19.2 million cross-border programme to restore peatlands and protect vital natural landscapes. Spearheaded by the con
Read More
19/10/2026
Adrian Pollock, operations director (Civils) at construction and civil engineering firm McLaughlin & Harvey, has been named Outstanding Contributor at the 2026 Northern Ireland Construction Awards. Run by the Construction Employers Federation (CEF), the prestigious awards bring together the sector
Read More
19/10/2026
Belfast City Council's Planning Committee has approved two new residential developments in west Belfast alongside permission for a new Lidl store in Dunmurry. One scheme, on lands near the Monagh By-pass, is a mixed-use project comprising two three-storey apartment blocks providing 36 social homes,
Read More
19/10/2026
Belfast Harbour is set to become a live test environment for next-generation zero-emission technologies following a £15m investment confirmed by Economy Minister Dr Caoimhe Archibald. The funding comes from UK Research and Innovation's (UKRI) Local Innovation Partnerships Fund (LIPF) and is the sec
Read More
Construction Information ServicesWTH SuppliesSLG Traffic ManagementO&O ConservatoriesSwords Auto [Traffic Management]Smart Heating Renewable SolutionsIreland T&T LtdRK EnviroDrain Jetters NiShanette Steel Frames