Construction News

12/05/2025

Works Progressing On Waterford North Quays Project

Works are currently progressing well for County Waterford's landmark North Quays project.

At a recent council meeting, Michael Quinn, Director of Economic Development, Waterford City and County Council, outlined that works are continuing in Ferrybank with the realigned Abbey Road and Dock Road due to be complete in July and October 2025, respectively.

Additionally, the transport hub is also positively progressing, with mechanical and electrical installation, platforms and landscaping ongoing.  Works to the platforms and rail track are continuing and the internal building fit out and external public entrance plaza at Dock Road will commence in the coming months. The transport hub is expected to be fully complete by Q2 2026 with final commissioning and opening by Irish Rail in early 2027.

The steel deck superstructure for the sustainable transport bridge, fabricated and fitted out at Victor Buyck Steel Construction's production plant in Ghent, Belgium, is due to be delivered by the end of May. The 207m bridge will be transported in four sections by sea-going barges from Ghent, via the Ghent–Terneuzen Canal, English Channel and Irish Sea to Belview Port and ultimately to the Waterford North Quays site. The delivery schedule is subject to final inspections as well as weather and sea conditions.

Once transported to Waterford, the rigging, lifting and installation procedures for the bridge will take around a week to complete. The bascule leaves for the opening central span will be tested and put into operation and finishing works, which include lighting, street furniture, and parapets, will commence once the bridge is installed and checked. The fast-tracking of integration works as part of construction of the Strategic Development Zone (SDZ) will facilitate the opening of the bridge to the public in Q4 2026.  Details of a bridge naming public consultation will be announced shortly.

-- Advertisement --

The public infrastructure project is being developed ahead of the private SDZ development and the built interface between the two developments must be fully integrated and compatible. The planning, design and construction of the public infrastructure project has therefore needed to be responsive to evolving progress and proposals for the private development in order to ensure proper management of the overall North Quays project and to de-risk the overall project in terms of cost and programme.

In April, Waterford City and County Council granted planning permission to Harcourt Developments (t/a Hopcast Limited) for the development of the first phase of the North Quays SDZ.

The mixed-use development will include significant residential accommodation, as well as office and hotel accommodation, retail offerings and high-quality public realm spaces consisting of:

• 350 residential units;

• Office accommodation including ground floor creche & retail;

• 160-bedroom hotel and conference centre;

• 163-room aparthotel;

• Retail units on ground floor of residential blocks;

• High quality public realm spaces to include public plazas, riverside boardwalk and greenway.

The SDZ development places a significant emphasis on connecting the north and south quays and improving the public realm through investment in new high quality civic spaces. The direct benefit to Waterford of the investment in the SDZ Site is anticipated to be in excess of €350m over the next six years, with 200 people employed during construction and upwards of 1,500 jobs to be created following completion of phase one of the development.

Drone footage of North Quays Public Infrastructure Project can be viewed here. 

Photo credit: Douglas Wallace.

Latest Construction News

14/08/2026
Economy Minister Dr Caoimhe Archibald has published the Department for the Economy's new Interconnection Policy Statement, setting the strategic direction for future East–West electricity infrastructure. The Statement aligns with the Executive's Energy Strategy, aiming to stimulate innovation and i
Read More
14/08/2026
NI Water has launched a major Water Infrastructure Improvement Scheme that will see around 17km of new water mains and associated connections installed across the Larne area. Most activity will take place in built-up residential parts of the town, alongside targeted enhancements to the rural netwo
Read More
14/08/2026
Deputy Lord Mayor of Cork Cllr. Gary O'Brien joined local Northeast Ward councillors and Cork City Council Chief Executive Valerie O'Sullivan to walk the new Glanmire Greenway. The route connects the recently completed link road at Dooley's Lane via the former John Barleycorn site and includes two
Read More
14/08/2026
MukAway, the materials management platform from MA EnviroTech Group, has agreed a three-year, group-wide deal with GRAHAM in one of the platform's largest commercial wins to date. The agreement brings the entire GRAHAM business onto MukAway, establishing it as the contractor's primary system for ma
Read More
14/08/2026
The latest phase of a major programme to improve water services in County Carlow has reached its midpoint. Crews have now installed 3km of the planned 6km of ageing watermains between Friarstown Pump Station and the N81/R727 junction at McGraths Cross. When this phase is complete, it will deliver a
Read More
14/08/2026
Liquid Corporate Finance has unveiled a fresh new brand identity, marking an exciting new chapter for the independent UK business finance broker. Since launching in 2019, Liquid Corporate Finance has continued to develop and establish itself within the UK business finance market. As the business ha
Read More
14/08/2026
Uisce Éireann is set to replace ageing water mains in Castletownbere this week, aiming to improve reliability and reduce leaks for local customers. Works along the L4935 and R572 at Felane West will see 2.3 kilometres of new, modern pipes installed to strengthen the network and minimise disruption
Read More
14/08/2026
SDLP North Belfast Councillor Carl Whyte has called for stronger planning, clearer communication and extra public transport to prevent fresh gridlock during upcoming M3 Lagan Bridge works. The SDLP representative warned there must be no recurrence of the severe traffic disruption witnessed during m
Read More
14/08/2026
The Green Party has called for data centres to shoulder the cost of modernising and expanding Ireland's electricity grid, rather than households. Deputy leader and party spokesperson for infrastructure and public expenditure, Cllr Hazel Chu, said a targeted levy on the sector should finance these
Read More
14/08/2026
Minister of State for Nature, Heritage and Biodiversity at the Department of Housing, Local Government and Heritage, Christopher O'Sullivan TD, has opened applications for three schemes for 2027: the Built Heritage Investment Scheme (BHIS), the Historic Structures Fund (HSF) and the Historic Thatche
Read More
Construction Information ServicesWTH SuppliesMaccaferri LtdTolVita LtdDGC Speed SprayA24 Security SystemsQuinn Crane Hire LimitedAC Cable SolutionsPipelife Ireland Solutions LimitedHLS