Subscribe to our Construction Newsfeed
Ireland Construction Directory
Search our 25,482 companies....

Construction News

21/05/2025

Significant Update On River Poddle Flood Alleviation Scheme

South Dublin County Council (SDCC) has provided an extensive update on the River Poddle Flood Alleviation Scheme.

Key highlights from the update include:

Tymon Park North

Embankment works have been completed with footpath reinstatement also completed. Landscaping works on the embankment are substantially complete with hedging to be planted front of the ESB Sub-Station in Q3 2025.The footpath along the embankment is scheduled to be re-opened in Q3 2025.

Tymon Park

Main Lake Area: The engineering works on the embankment are 100% complete and the landscaping element has commenced with the levelling and reseeding of impacted areas. Works are yet to be completed on safety features and footpath installations but will be re-commencing shortly, with tree planting to commence in Q3 2025.

Once the safety features and footpath installations are complete and the grass seeding has been given time to establish, this area will be re-opened to the public. This is currently expected to be in September 2025.

Integrated Constructed Wetland Area: The engineering works on the Integrated Constructed Wetland are 100% complete with a low level of re-planting identified as being required.

Landscaping works have recommenced along with the introduction of ecological enhancements such as a sand martin bank and a kingfisher box. Some landscaping, site signage and footpath installation works are still required to be completed, which is currently estimated to take 4-6 weeks to complete. These works are weather dependant.

-- Advertisement --

Based on the above it is currently expected that access to this area of the park will re-open in mid July 2025.

The project team are striving in getting the impacted areas of Tymon Park re-opened to the public as soon as possible but unsuitable ground conditions earlier in the year have delayed the completion of landscaping and finishes works. Once these works are completed, an update will be further provided as to re-opening dates.

Whitehall/Wainsfort

The works are continuing in the Wainsfort area with the required tree and vegetation removal along the riverbank in Wainsfort, at the rear of the Whitehall Rd properties and at the Badminton Centre completed in January 2025 with the flood defence works commencing in February.

Badminton Centre: The reinforced concrete defence wall has recently been completed with cladding works to commence in late June and are expected to be finished in August.

Wainsfort Weir Area: Works are ongoing at the weir with the extension to the weir walls completed in April.

Reinforced concrete works to the defence walls adjacent to the weir have commenced and are expected to be completed in early Q3 2025. Once concrete works have been completed, cladding works will commence.

The defence works in Wainsfort are expected to take a further eight months to fully complete along with four months to complete the landscaping.

Ravensdale Park

The flood defence works in Ravensdale Park will commence in May 2025 where access restrictions to the Northern end of the park will be put in place, with the access points at Ravensdale Drive, Ravensdale Park and Kimmage Road Lower being closed. The access from Kimmage Road Lower to Kimmage Road West will remain open during the works.

The full package of works in Ravensdale Park are expected to take 12 months to complete.

St Martin's Drive

Works are currently expected to commence here in Q1 2026. 

The council also confirmed that 45% of the flood defences on the scheme have now been installed to date. 

A statement from SDCC said: "We fully understand that the works have been and will be, an inconvenience but because of the works completed since May 2024 and with the flow control structure in Tymon Park coming into operation since February 2025, instant flood relief benefit has now been provided to a high number of properties from future rainfall events."

Latest Construction News

14/08/2026
Economy Minister Dr Caoimhe Archibald has published the Department for the Economy's new Interconnection Policy Statement, setting the strategic direction for future East–West electricity infrastructure. The Statement aligns with the Executive's Energy Strategy, aiming to stimulate innovation and i
Read More
14/08/2026
NI Water has launched a major Water Infrastructure Improvement Scheme that will see around 17km of new water mains and associated connections installed across the Larne area. Most activity will take place in built-up residential parts of the town, alongside targeted enhancements to the rural netwo
Read More
14/08/2026
Deputy Lord Mayor of Cork Cllr. Gary O'Brien joined local Northeast Ward councillors and Cork City Council Chief Executive Valerie O'Sullivan to walk the new Glanmire Greenway. The route connects the recently completed link road at Dooley's Lane via the former John Barleycorn site and includes two
Read More
14/08/2026
MukAway, the materials management platform from MA EnviroTech Group, has agreed a three-year, group-wide deal with GRAHAM in one of the platform's largest commercial wins to date. The agreement brings the entire GRAHAM business onto MukAway, establishing it as the contractor's primary system for ma
Read More
14/08/2026
The latest phase of a major programme to improve water services in County Carlow has reached its midpoint. Crews have now installed 3km of the planned 6km of ageing watermains between Friarstown Pump Station and the N81/R727 junction at McGraths Cross. When this phase is complete, it will deliver a
Read More
14/08/2026
Liquid Corporate Finance has unveiled a fresh new brand identity, marking an exciting new chapter for the independent UK business finance broker. Since launching in 2019, Liquid Corporate Finance has continued to develop and establish itself within the UK business finance market. As the business ha
Read More
14/08/2026
Uisce Éireann is set to replace ageing water mains in Castletownbere this week, aiming to improve reliability and reduce leaks for local customers. Works along the L4935 and R572 at Felane West will see 2.3 kilometres of new, modern pipes installed to strengthen the network and minimise disruption
Read More
14/08/2026
SDLP North Belfast Councillor Carl Whyte has called for stronger planning, clearer communication and extra public transport to prevent fresh gridlock during upcoming M3 Lagan Bridge works. The SDLP representative warned there must be no recurrence of the severe traffic disruption witnessed during m
Read More
14/08/2026
The Green Party has called for data centres to shoulder the cost of modernising and expanding Ireland's electricity grid, rather than households. Deputy leader and party spokesperson for infrastructure and public expenditure, Cllr Hazel Chu, said a targeted levy on the sector should finance these
Read More
14/08/2026
Minister of State for Nature, Heritage and Biodiversity at the Department of Housing, Local Government and Heritage, Christopher O'Sullivan TD, has opened applications for three schemes for 2027: the Built Heritage Investment Scheme (BHIS), the Historic Structures Fund (HSF) and the Historic Thatche
Read More
WTH SuppliesConstruction Information ServicesFernhill StoneYardBoxTech Fab EngineeringVision Creative StudiosIrish Crane & Lifting LimitedLoocube.ieSiteCrew LTDJK Home Improvements