Subscribe to our Construction Newsfeed
Ireland Construction Directory
Search our 25,488 companies....

Construction News

21/05/2025

Significant Update On River Poddle Flood Alleviation Scheme

South Dublin County Council (SDCC) has provided an extensive update on the River Poddle Flood Alleviation Scheme.

Key highlights from the update include:

Tymon Park North

Embankment works have been completed with footpath reinstatement also completed. Landscaping works on the embankment are substantially complete with hedging to be planted front of the ESB Sub-Station in Q3 2025.The footpath along the embankment is scheduled to be re-opened in Q3 2025.

Tymon Park

Main Lake Area: The engineering works on the embankment are 100% complete and the landscaping element has commenced with the levelling and reseeding of impacted areas. Works are yet to be completed on safety features and footpath installations but will be re-commencing shortly, with tree planting to commence in Q3 2025.

Once the safety features and footpath installations are complete and the grass seeding has been given time to establish, this area will be re-opened to the public. This is currently expected to be in September 2025.

Integrated Constructed Wetland Area: The engineering works on the Integrated Constructed Wetland are 100% complete with a low level of re-planting identified as being required.

Landscaping works have recommenced along with the introduction of ecological enhancements such as a sand martin bank and a kingfisher box. Some landscaping, site signage and footpath installation works are still required to be completed, which is currently estimated to take 4-6 weeks to complete. These works are weather dependant.

-- Advertisement --

Based on the above it is currently expected that access to this area of the park will re-open in mid July 2025.

The project team are striving in getting the impacted areas of Tymon Park re-opened to the public as soon as possible but unsuitable ground conditions earlier in the year have delayed the completion of landscaping and finishes works. Once these works are completed, an update will be further provided as to re-opening dates.

Whitehall/Wainsfort

The works are continuing in the Wainsfort area with the required tree and vegetation removal along the riverbank in Wainsfort, at the rear of the Whitehall Rd properties and at the Badminton Centre completed in January 2025 with the flood defence works commencing in February.

Badminton Centre: The reinforced concrete defence wall has recently been completed with cladding works to commence in late June and are expected to be finished in August.

Wainsfort Weir Area: Works are ongoing at the weir with the extension to the weir walls completed in April.

Reinforced concrete works to the defence walls adjacent to the weir have commenced and are expected to be completed in early Q3 2025. Once concrete works have been completed, cladding works will commence.

The defence works in Wainsfort are expected to take a further eight months to fully complete along with four months to complete the landscaping.

Ravensdale Park

The flood defence works in Ravensdale Park will commence in May 2025 where access restrictions to the Northern end of the park will be put in place, with the access points at Ravensdale Drive, Ravensdale Park and Kimmage Road Lower being closed. The access from Kimmage Road Lower to Kimmage Road West will remain open during the works.

The full package of works in Ravensdale Park are expected to take 12 months to complete.

St Martin's Drive

Works are currently expected to commence here in Q1 2026. 

The council also confirmed that 45% of the flood defences on the scheme have now been installed to date. 

A statement from SDCC said: "We fully understand that the works have been and will be, an inconvenience but because of the works completed since May 2024 and with the flow control structure in Tymon Park coming into operation since February 2025, instant flood relief benefit has now been provided to a high number of properties from future rainfall events."

Latest Construction News

19/11/2026
Farrans is recruiting a further 40 graduates, placement students and apprentices after securing several significant contracts, taking its planned early careers intake for 2027 to 100. Applications opened in September and close in December. The company said on 18 November that approximately two week
Read More
19/11/2026
Radius Housing brought together organisations from the health, care and support sectors for a conference focused on collaboration and supported housing. Representatives from Praxis Care, Mencap, the Simon Community and local Health and Social Care Trusts attended the event. They exchanged ideas and
Read More
19/11/2026
Uisce Éireann is to survey part of Mayo’s underground drinking water network using specialist technology designed to minimise disruption to customers. The work is scheduled for today, 19 November, on the trunk main between Lough Mask Water Treatment Plant in Tuar Mhic Éadaigh and Castlebar Reservoi
Read More
19/11/2026
Pupils at Corbiewood Primary School have entered their new building for their first day of lessons. The school will serve the developing South Stirling Gateway community. It is the first new school built in the Stirling Council area to accommodate population growth since Newton Primary School opene
Read More
19/11/2026
Civil and structural engineering consultancy Will Rudd has secured two new local authority appointments in Kerry and Waterford, supporting the delivery of 100 social homes across the two counties. The latest commissions include a 22-home development at Spunkane, Waterville, for Kerry County Council
Read More
19/11/2026
Galway City Council has published its draft budget for 2027, proposing a €176.5 million revenue budget alongside a capital programme worth more than €100 million. The proposals cover housing, transport, climate action, economic development, community facilities, improvements to public spaces and es
Read More
19/11/2026
A property developer has been fined £50,000 following the unauthorised demolition of listed buildings at Brookfield House in Banbridge, after enforcement action by Armagh City, Banbridge and Craigavon Borough Council's planning department. Enniskillen-based BIG Contracts Ltd was fined at Newry Magi
Read More
19/11/2026
A Leitrim woman is helping to plan Ireland's future electricity network as EirGrid marks 25 years in operation. Edel Campbell, from Drumshanbo, is a network planning manager at the organisation, which operates the electricity transmission system and plans and delivers grid infrastructure. She joine
Read More
19/11/2026
The Irish Government has approved a €20 million fuel support scheme for the construction and quarrying sectors, with payments due in 2027. Applications will open in early December. The scheme follows measures announced earlier in 2026 for farmers, fishers and agricultural contractors using Marked G
Read More
19/11/2026
Ireland's Housing Minister James Browne has announced more than €90 million in relocation funding for two housing sites at Colbert Quarter in Limerick and Sandy Quarter in Galway. The funding will support the relocation of services operated by the HSE, Limerick City and County Council, Galway Count
Read More
WTH SuppliesConstruction Information ServicesFP McCann LtdContainexADM Floor ScreedLoughtec Cyber SecuritySkill Ireland TrainingGalvin Ceilings & PartitionsTIMONEY WINDOWSEcocel