Significant Update On River Poddle Flood Alleviation Scheme

South Dublin County Council (SDCC) has provided an extensive update on the River Poddle Flood Alleviation Scheme.

Key highlights from the update include:

Tymon Park North

Embankment works have been completed with footpath reinstatement also completed. Landscaping works on the embankment are substantially complete with hedging to be planted front of the ESB Sub-Station in Q3 2025.The footpath along the embankment is scheduled to be re-opened in Q3 2025.

Tymon Park

Main Lake Area: The engineering works on the embankment are 100% complete and the landscaping element has commenced with the levelling and reseeding of impacted areas. Works are yet to be completed on safety features and footpath installations but will be re-commencing shortly, with tree planting to commence in Q3 2025.

Once the safety features and footpath installations are complete and the grass seeding has been given time to establish, this area will be re-opened to the public. This is currently expected to be in September 2025.

Integrated Constructed Wetland Area: The engineering works on the Integrated Constructed Wetland are 100% complete with a low level of re-planting identified as being required.

Landscaping works have recommenced along with the introduction of ecological enhancements such as a sand martin bank and a kingfisher box. Some landscaping, site signage and footpath installation works are still required to be completed, which is currently estimated to take 4-6 weeks to complete. These works are weather dependant.

-- Advertisement --

Based on the above it is currently expected that access to this area of the park will re-open in mid July 2025.

The project team are striving in getting the impacted areas of Tymon Park re-opened to the public as soon as possible but unsuitable ground conditions earlier in the year have delayed the completion of landscaping and finishes works. Once these works are completed, an update will be further provided as to re-opening dates.

Whitehall/Wainsfort

The works are continuing in the Wainsfort area with the required tree and vegetation removal along the riverbank in Wainsfort, at the rear of the Whitehall Rd properties and at the Badminton Centre completed in January 2025 with the flood defence works commencing in February.

Badminton Centre: The reinforced concrete defence wall has recently been completed with cladding works to commence in late June and are expected to be finished in August.

Wainsfort Weir Area: Works are ongoing at the weir with the extension to the weir walls completed in April.

Reinforced concrete works to the defence walls adjacent to the weir have commenced and are expected to be completed in early Q3 2025. Once concrete works have been completed, cladding works will commence.

The defence works in Wainsfort are expected to take a further eight months to fully complete along with four months to complete the landscaping.

Ravensdale Park

The flood defence works in Ravensdale Park will commence in May 2025 where access restrictions to the Northern end of the park will be put in place, with the access points at Ravensdale Drive, Ravensdale Park and Kimmage Road Lower being closed. The access from Kimmage Road Lower to Kimmage Road West will remain open during the works.

The full package of works in Ravensdale Park are expected to take 12 months to complete.

St Martin's Drive

Works are currently expected to commence here in Q1 2026. 

The council also confirmed that 45% of the flood defences on the scheme have now been installed to date. 

A statement from SDCC said: "We fully understand that the works have been and will be, an inconvenience but because of the works completed since May 2024 and with the flow control structure in Tymon Park coming into operation since February 2025, instant flood relief benefit has now been provided to a high number of properties from future rainfall events."

Latest Construction News

01/10/2026
Elgin has completed the acquisition of the approximately 200MW Blackhall Solar Farm in County Meath from GP Joule, strengthening the company's late-stage renewable energy development pipeline in Ireland. The project is a late-stage, consented solar development with grid connection arrangements alre
Read More
01/10/2026
Tipperary County Council has confirmed a temporary nightly closure of the N24 between Knockagh and Derrygrath to facilitate a pavement improvement scheme. Closures will operate Monday to Friday from 19:30 to 06:00. While the original schedule ran from Monday 28 September to Friday 16 October 2026,
Read More
01/10/2026
Clare County Council has teamed up with EnergyCloud and FuturEnergy Ireland on a trial that redirects excess green power from the national grid to provide free hot water for social housing tenants near the Carrownagowan Wind Farm. Under the scheme, EnergyCloud smart devices will be installed in 40
Read More
01/10/2026
Uisce Éireann has welcomed the Environmental Protection Agency's decision to grant the licence for the Greater Dublin Drainage Project, calling it a major milestone and one of the final statutory approvals needed for the scheme. The project is designed to expand wastewater treatment for growing com
Read More
01/10/2026
Dún Laoghaire-Rathdown County Council has authorised John Paul Construction to carry out works outside normal construction hours at Dún Brí (the Dundrum Mental Hospital site) to deliver, install and erect a tower crane over the weekend of 3 and 4 October. The approved working hours are: Saturday 3
Read More
01/10/2026
€5 million in pre-construction support from the Climate Action Fund has been approved for nine public and private district heating schemes across seven counties, aiming to accelerate a pipeline of projects ahead of larger capital investment. Minister for Climate, Energy and the Environment Darragh
Read More
01/10/2026
The Northern Ireland Audit Office has published a strategic review identifying substantial backlogs and lengthy delays at the Planning Appeals Commission (PAC), which are hindering the planning system's ability to support economic and environmental development in Northern Ireland. The PAC handles p
Read More
01/10/2026
Early public engagement on the Newry Inner City Greenway Active Travel Signature Scheme will begin on 8 October 2026, the Department for Infrastructure has confirmed. Announcing the move, Infrastructure Minister Liz Kimmins said: "This signature active travel scheme aims to improve connectivity for
Read More
01/10/2026
Mayo County Council has issued a notice of its intention to temporarily close part of Church Road / Bonnifinglas Road (L-1321) to facilitate cable duct installation for the North Connaught 110kV Interconnector Project. The proposed closure covers a section of Church Road (L-1321) between the L1324
Read More
01/10/2026
Sinn Féin’s spokesperson on Climate, the Environment and Energy, Pa Daly TD, has criticised the Government's newest energy package, saying it does not tackle the drivers of high bills. He called for the rapid reinstatement of energy credits to deliver urgent support to families. Daly argued the c
Read More
WTH SuppliesConstruction Information ServicesBOLTSANDNUTS.IEUnique Garden RoomsJK Home ImprovementsVision Creative StudiosVisual Precision LtdOne Stop Handling Ireland LtdCuchulainn WorkwearForde Seamless Gutters