€88m Killaloe Bypass Road Project Officially Opens

The transformative €88m Killaloe Bypass road project has officially been opened by Minister for Transport, Darragh O'Brien.

The 6.2km development, located in the vicinity of the twin towns of Killaloe, Co Clare and Ballina, Co Tipperary, includes the first new vehicular bridge across the River Shannon in more than three decades.

The bridge, known as the Brian Ború Bridge, was a complex engineering feat for those involved in the project that took 2.5 years to complete.

It provides a western bypass of Killaloe and an upgrade of the existing R494 regional road from Ballina to the N7 at Birdhill.

Speaking at the opening, Minister for Transport, Darragh O'Brien, said: "I am delighted to officially open this transformative road project, which strengthens the connection between communities in Clare and Tipperary. With approximately €88m million in funding allocated by my Department, this represents a significant Government investment in regional infrastructure and underscores our ongoing commitment to investing in and modernising Ireland's road network.

-- Advertisement --

"Road safety remains a key priority in all our infrastructure projects. The completion of the Killaloe Bypass will significantly enhance safety and efficiency for all road users. The inclusion of dedicated pedestrian and cycling facilities not only improves safety but also encourages more sustainable, active travel along this vital corridor."

The scheme will greatly improve the quality of life for residents of both towns. The alternative route will take through traffic and HGVs out of both town centres, thereby significantly reducing congestion, protecting both heritage areas, and providing a much-needed boost to the local economy and the region’s tourism sector.

The project was listed in the National Development Plan and comprises:

• Two km of new single carriageway bypass around the town of Killaloe which connects the R463 to the north of the town with the Brian Ború Bridge section and R494 to the south of the town;

• A new single carriageway bridge named in honour of Brian Ború crossing over the River Shannon approximately 1km south of the existing Killaloe Bridge and connecting the Killaloe Bypass with the R494;

• The upgrade and realignment of approximately 3.3 kilometres of the existing R494 from its junction with the R496 and Brian Ború Bridge south of Ballina, as far as the junction with the R445 (previously known as N7) north of Birdhill, and the M7 link road;

• Provision of dedicated, high quality new cycling and pedestrian facilities along the approximately 6.2km length of road development;

• The new Brian Ború bridge over the Shannon at Ballina-Killaloe is the first new vehicular bridge across the river since the opening of Shannon Way Bridge in 1991, which connects Athlone Westmeath County Council to the east and Roscommon County Council to the west.

Photo credit: Paul Corey.

Latest Construction News

01/10/2026
Elgin has completed the acquisition of the approximately 200MW Blackhall Solar Farm in County Meath from GP Joule, strengthening the company's late-stage renewable energy development pipeline in Ireland. The project is a late-stage, consented solar development with grid connection arrangements alre
Read More
01/10/2026
Tipperary County Council has confirmed a temporary nightly closure of the N24 between Knockagh and Derrygrath to facilitate a pavement improvement scheme. Closures will operate Monday to Friday from 19:30 to 06:00. While the original schedule ran from Monday 28 September to Friday 16 October 2026,
Read More
01/10/2026
Clare County Council has teamed up with EnergyCloud and FuturEnergy Ireland on a trial that redirects excess green power from the national grid to provide free hot water for social housing tenants near the Carrownagowan Wind Farm. Under the scheme, EnergyCloud smart devices will be installed in 40
Read More
01/10/2026
Uisce Éireann has welcomed the Environmental Protection Agency's decision to grant the licence for the Greater Dublin Drainage Project, calling it a major milestone and one of the final statutory approvals needed for the scheme. The project is designed to expand wastewater treatment for growing com
Read More
01/10/2026
Dún Laoghaire-Rathdown County Council has authorised John Paul Construction to carry out works outside normal construction hours at Dún Brí (the Dundrum Mental Hospital site) to deliver, install and erect a tower crane over the weekend of 3 and 4 October. The approved working hours are: Saturday 3
Read More
01/10/2026
€5 million in pre-construction support from the Climate Action Fund has been approved for nine public and private district heating schemes across seven counties, aiming to accelerate a pipeline of projects ahead of larger capital investment. Minister for Climate, Energy and the Environment Darragh
Read More
01/10/2026
The Northern Ireland Audit Office has published a strategic review identifying substantial backlogs and lengthy delays at the Planning Appeals Commission (PAC), which are hindering the planning system's ability to support economic and environmental development in Northern Ireland. The PAC handles p
Read More
01/10/2026
Early public engagement on the Newry Inner City Greenway Active Travel Signature Scheme will begin on 8 October 2026, the Department for Infrastructure has confirmed. Announcing the move, Infrastructure Minister Liz Kimmins said: "This signature active travel scheme aims to improve connectivity for
Read More
01/10/2026
Mayo County Council has issued a notice of its intention to temporarily close part of Church Road / Bonnifinglas Road (L-1321) to facilitate cable duct installation for the North Connaught 110kV Interconnector Project. The proposed closure covers a section of Church Road (L-1321) between the L1324
Read More
01/10/2026
Sinn Féin’s spokesperson on Climate, the Environment and Energy, Pa Daly TD, has criticised the Government's newest energy package, saying it does not tackle the drivers of high bills. He called for the rapid reinstatement of energy credits to deliver urgent support to families. Daly argued the c
Read More
Construction Information ServicesWTH SuppliesS & N GraniteGrantNexventurEMKO Industrial LtdAIM Engineering & Fabrications LtdNW RenewablesConstruction Information ServicesSeamless Aluminium Group