05/12/2008

'Significant Progress' On Dungannon £5.5m Roads Improvement

Construction News Image
Northern Ireland Roads Minister Conor Murphy has detailed the progress on a £5.5m maintenance and local transport scheme in the Dungannon area.

Work on the A4 Dungannon to Ballygawley dual carriageway and single carriageway realignments on the Ballygawley to Aughnacloy and Ballygawley to Augher roads began earlier this year.

Mr Murphy said construction has largely focused on the Ballygawley end of the project with the excavation and reuse of one million tonnes of material.

"A number of structures which carry the new road over the minor roads are nearing completion namely Armalaughey Road, Goland Road and Farriter Road," said the Minister.

He said: "Others on the Killeeshil Road, Coolhill Road and Cravenny are at various stages of construction."

Mr Murphy said work on the A5 Western Key Transport Corridor continues to make "significant progress".

-- Advertisement --

Details of the preferred corridor for this scheme were announced last month.

"Roads Service will now be developing a number of route options within the preferred corridor and a series of public consultation events will be held in early 2009 to highlight these options and to invite comments," said the Minister.

Realignment works between Dungannon and Cookstown the A29 Carland Bridge will begin in May 2009, with the procurement process already underway, said Mr Murphy.

"Schemes which have been completed this financial year include the resurfacing in asphalt of 1,800 metres of the A5 Tullyvar Road, resurfacing of the A29 Dungannon Road, Moy and bitmac resurfacing of 1,800 metres of the Whitebridge Road.

"Also completed has been the provision of a right turning lane on the A29 at the Moy Road / Old Moy Road junction in Dungannon and the provision of a pelican crossing at Colebrooke Road, Fivemiletown," he added.

Road Service’s Divisional Roads Manager, Pat Doherty, said: "Other schemes that will be taken forward in the current financial year include the completion of a double right turning lane and footway on the A4 at Killeeshil Crossroads and improvements to the existing footpath in Ardbeg, Dungannon.

The Roads Service report also contained the draft capital programme for 2009-2011.

Schemes including junction improvements on the B43 at the Mullaghmore Road / Tullydraw Road junction and providing footway and cycle links on the Killyman Road in Dungannon.

(PR/JM)

Latest Construction News

03/05/2024

Construction work has commenced on a new £9 million build at Rowandale Integrated Primary School in Moira. Funding from the Fresh Start Programme will facilitate the establishment of a new, modern primary school, with 14 classrooms and a nursery unit capable of accommodating over 340 ...
03/05/2024

Minister for Agriculture, Food and the Marine, Charlie McConalogue T.D. together with Leas Chathaoirleach of Donegal County Council, Cllr Gerry McMonagle, has opened the Greencastle Harbour Breakwater. The 270-metre Breakwater aims to improve the protection of vessels in the harbour against wave ...
03/05/2024

NI Water has initiated a £3.5 million improvement programme at Newcastle Wastewater Treatment Works (WwTW). Murphy Dawson Wam JV is undertaking the project, which focuses on improving the three-stage treatment process at the current facility. This will entail installing new filtration gear and a ...
03/05/2024

Bennett Construction has announced that it has achieved Practical Completion (PC) on the Tristan Square Development in Chapelizod, Dublin. The project includes the construction of 180 social and affordable apartments split in to one, two and three bed homes over three blocks. Each of the units are ...
03/05/2024

SSE Renewables and FuturEnergy Ireland have revealed that Microsoft has committed to a lengthy Corporate Power Purchase Agreement (CPPA) with the co-developers. This agreement will inject 30MW of wind energy into Ireland's power grid through the recently launched Lenalea Wind Farm, located near ...
03/05/2024

Farrans has announced that it has collected three awards, including one Gold, at the Considerate Constructor Scheme's National Awards. The CCS National Awards honour outstanding sites, organisations and people who show exceptional commitment to the Code of Considerate Practice in Community, ...
03/05/2024

County Down headquartered GRAHAM has started construction work on a new £59 million low-carbon development in Edinburgh. The Burnet Point scheme in Abbey Lane which combines student flats, build-to-rent and affordable homes is the first-ever mixed-use residential development of its kind by Unite ...
03/05/2024

Alliance's Housing spokesperson, Kellie Armstrong MLA, has welcomed the NI Federation of Housing Associations (NIFHA) commitment to reduce carbon emissions in social homes and combat climate change. Housing associations are currently in the process of developing a scheme set to launch this autumn. ...
03/05/2024

Fibrus has announced that it has exceeded its 80,000 customer milestone, as it gains over 50,000 customers in just one year. The broadband provider burst on to the scene to transform the digital infrastructure of rural and regional areas of Northern Ireland and has shaken up the market due to its ...
03/05/2024

Infrastructure Minister, John O'Dowd, has announced his support for the 'No Mow May' approach to help promote biodiversity on the roadside during this month. The Department for Infrastructure oversees the maintenance of 45,000km of grass verges along the road network. In recent years, it has been ...
Toner Damp Proofing SuppliesMcHale Plant Sales LtdFITACTool FixShannonside GalvanizingCarlow Concrete TanksSlanetracGS Concrete PumpingGarden and Home FxFox Excavations & Plant Hire
Terms and Conditions
2024/05/04 19:34:58