A major water infrastructure project serving Newbridge is entering its final stages, with more than 7.5km of a new main installed along the 10km route between Two Mile House and Great Connell.
Uisce Éireann said the investment will increase network capacity for future housing and planned growth. The pipeline is also intended to ease pressure on the existing network and improve the reliability of supplies for current customers.
Uisce Éireann's Derek Deignan said: "We're making great progress since works began in April, with 7.5km of the new water main now in place. Permanent road resurfacing and line marking have been completed between Corbally and Two Mile House.
"We're now moving into the final stages of the project and appreciate the patience of the local community while we complete this work. This is an important investment in Newbridge’s water infrastructure, increasing capacity in the network to help support new homes and the continued growth of the area."
Temporary road closures will continue in phases so crews can complete the remaining work safely. Work is taking place on Harbour Road and is due to move to Great Connell Road towards Newbridge early next year.
The road closure will be lifted temporarily from 18 December 2026 until 4 January 2027, restoring normal access for residents, visitors and local traffic over Christmas. Uisce Éireann said its crews would work to minimise disruption to people living and travelling along the route.
Shareridge is carrying out the project on behalf of Uisce Éireann, with completion expected in 2027. Some brief water supply interruptions may be necessary as work progresses; customers will receive at least 48 hours’ notice of any planned interruption.