NI Water and its contractor BSG Civil Engineering is to start the final connections and commissioning work on a new pumping station in Ballymartin, Co Down.
The facility, at Annalong Road in Blackrock, is part of a £1.2 million investment by Irish Water.
The work includes the laying of new pipelines between Blackrock and Ballymartin. The overall scheme will collect wastewater from the Blackrock and Ballymartin areas and transfer it to Kilkeel for treatment. The new infrastructure will bring about environmental benefits in the area and will accommodate future development in the village for the next 20 years.
To facilitate the work temporary lane closures will be implemented with automated traffic lights on a short section of the Annalong Road around the location of the new pumping station.
A lane closure will be in place from Monday 12 September until Friday 17 September for pipeline connections. A further short lane closure will be sought at a later date to allow the electrical contractor to complete work at the pumping station.
(CD/MH)
Ireland
UK
Scotland
London





![Swords Auto [Traffic Management]](http://www.construction.co.uk/advnew/489306bul.jpg)