Construction work is to start on a £250,000 road improvement project in Bangor, Co Down.
The work, on the Rathgael Road, is to begin on Saturday, 12 August.
The resurfacing scheme, which incorporates embankment sidefilling, will improve the strength and surface quality of the carriageway on a 550 metre section of this important C class link road on the outskirts of Bangor.
Resurfacing will be carried out over the following weekends with a full road closure in place:
• 12-13 August
• 19-20 August
• 02-03 September
• 09-10 September
From 14 August for four weeks, a one-way mid-week road closure will operate, permitting access from the A2 Belfast Road towards Rathgael Road Roundabout. Traffic seeking access to the A2 from Rathgael Road will be diverted via the Clandeboye Road, A2 West Circular Road.
Local access will be maintained and diversions will be put in place during the works.
(CD/LM)