Construction work has started to reduce flooding near Clady Village in Co Tyrone.
The first phase of the £470,000 flood alleviation scheme is taking place in the Stephenstown area.
Approximately 100 metres of new pipeline will be installed with associated outlet structure and flood protection to the rear of two properties on the Urney Road. The works are expected to be complete by the end of summer 2018.
The second phase of the works includes 520 metres of earthen flood defence to the rear of additional properties on Urney Road. These works are programmed to commence late summer 2018 with completion by March 2019.
(CD/LM)