BSG Civil Engineering has completed sewer laying work in Malfin Drive, Belfast.
Work will now move into Upper Malone Park, where it will take eight weeks to finish.
The work is part of the major £4 million Flood Alleviation Project in the Greystown/Malone area.
The scheme involves the upgrading of the existing combined sewers and the DfI Rivers culvert from Upper Malone Road to Finnis Close.
Road closures will be in place throughout the duration of the work in Upper Malone Park.
The entire scheme is expected to be completed in 18 months.