Work is progressing on the M7 upgrade project, with mainline traffic to be gradually moved beginning today, 15 November.
The traffic will move between Junction 10 – 9 and will continue section by section as the works progress.
It will be completed across two stages.
The first stage will include splitting the two traffic lanes in order to complete the middle lane of each carriageway with the second stage moving both lanes across onto the new surface.
Two lanes will be maintained during peak hours at all times.
Once traffic has been moved across, works will commence in the adjacent verge/hard shoulder areas which will include for the tie in of new slip lanes.
(CM/MH)