NI Water's project to build a £3 million water main in Co Fermanagh has entered its final phase of works.
The new main will be located between Ally Hill Service Reservoir (SR), on the outskirts of Lough Bradan and Doochrock and Drumkeeran SRs near Ederney.
It will help improve the local water supply, transporting drinking water from Ally Hill Service Reservoir and continuing on to Doochrock and Drumkeeran Service Reservoirs.
Work is progressing in private lands and the final section of works, along Tirmacsprid Road, is due to get underway in March and continue through April.
BSG Civil Engineering is delivering the project on behalf of the utility.
The works are due for completion in May 2019.
(CM/JG)