ShareRidge is progressing work on a €12 million water mains renewal programme across County Donegal.
Completed work includes a 2.4km water main, transfer of service connections, road reinstatement and the decommissioning of the old in Carlin and Kerrykeel.
The installation of water main, transfer of service connections, temporary road reinstatement and decommissioning of the old main is also complete in Doaghmore, Fanad, Meenaleck, Ranafast, and Sheskinbeg.
Works are ongoing at Derrybeg, Brinnalack, Argery, Ballindrait, Lifford and Ballybofey South Backline, with other projects in Bundoran West, Corker and Ballyshannon scheduled to get underway in the next couple of months.
The remaining schemes currently at design stage include Abbeylands, Ballyshannon, Three Trees, Quigleys Point, Cabry and Redcastle.
Construction work on the county-wide project began in September 2018 and is on track for completion by the end of 2019.
(CM)