Work is to commence on a £80,000 road resurfacing project in L'Derry.
The work on the B523 Chapel Road will begin on Monday, 19 October.
The work will start near the Spencer Road junction and progress southwards to Fountain Hill for a distance of approximately 500 metres and will greatly improve the strength and surface quality of the road and footways.
The kerbing and drainage work will be carried out under temporary traffic control measures between 8am to 5pm from 19 October to the 23 October.
The road will be closed from 8am on Monday 26 October to 6pm on Tuesday 3 November.
A diversion route will be signposted via U 1500 Spencer Road, A1002 Duke Street, A1002 Waterside Link, A1002 King Street, A6 Glendermott Road, A6 Dungiven Road, A6 Altnagelvin Roundabout, A514 Irish Street and B523 Irish Street. Local access for residents will be maintained although delays can be expected.