Work is to start on a £350,000 carriageway resurfacing scheme in Irvinestown.
The work will take place on a section of the A32 Tummery Road Irvinestown at Drumharvey on Monday, 23 November.
The scheme extends for a distance of approximately 1.2 kilometres from the speed limits in Irvinestown towards Dromore and includes resurfacing of the carriageway, upgrading of road drainage and improvement to the Tullynincrin Road Junction.
Preparatory works are already underway however in order to facilitate the resurfacing works it will be necessary to operate a daily weekday road closure from Monday 23 November until Friday 04 December between the hours of 9.30 am and 4.30 pm. Local access for residents will be maintained at all times although some delays may be experienced.
During the closures a two way diversion will be in operation. Traffic travelling from Dromore will be diverted via Fintona Road; Galbally Road; Main Street, Trillick; Kilskeery Road; Main Street, Ballinamallard; Enniskillen Road to A32 Mossfield Road. Traffic travelling from Irvinestown will be diverted via A35 Kesh Road; B72 Manoo Road; B4 Letterboy Road; Ederney; B4 Edenamobil Road; Lack; B4 Drumlish Road to A32 Clannabogan Road.
A further road closure will be required in the New Year to facilitate the laying of the final surface layer.
Completion of the first phase of the works by 05 December.