Work is to commence on a £380,000 carriageway resurfacing scheme in Armagh.
The improvement work, which starts on 26 July, will extend approximately 1.1 kilometre from its junction with Mullacreevie housing estate to its junction with the A3 at the Irish Street slip road link to include 250 metres of new street lighting.
Infrastructure Minister Nichola Mallon said: "This significant investment will greatly improve the strength and surface quality of this section of the road network in to the benefit of all who use it. I would like to thank local residents and businesses in advance for their cooperation and ask that they comply with all temporary traffic restrictions while these much needed works are completed."
Temporary traffic signals will be put in place between the hours of 9am and 5pm from Monday 26 July until Friday 6 August (Monday to Friday only). Following this a closure will be in place from 9am until 5pm each day from Monday 9 August until Friday 20 August 2021. The road will be open evenings and at weekends.
During periods of closure traffic will be diverted via the A3 Slip Road North, A3 Irish Street, A3 Monaghan Road, B210 Coolkill Road and A28 Killylea Road
Local access for residents and emergency services will be maintained at all times.
The work is expected to be complete on 20 August.