Construction work has started on a £226,000 carriageway and footway resurfacing project on Milltown Avenue in Derriaghy, Lisburn.
The work commenced on Monday 26 July and is expected to be complete by 29 October.
The resurfacing scheme, which stretches from Belsize Road to the Milltown Road for 937 metres will deliver significant benefits for road users.
Infrastructure Minister Nichola Mallon said: "This significant investment will greatly improve the strength and surface quality of this section of the road network to the benefit of local residents and those who travel through the area. I would like to thank the public and local residents in advance for their cooperation and ask that they comply with all temporary traffic restrictions while these much needed works are completed."
Lane closures will be operational each weekday (Monday – Friday from 8am until 6pm). Local access for residents and emergency services will be maintained at all times.