A key project to end the discharge of untreated wastewater into Castlehaven Harbour, Co Cork, is continuing to make significant progress.
Uisce Éireann and Cork County Council are working to develop new wastewater infrastructure for the Castletownshend area.
Speaking about the project to date, Anthony Kavanagh, Programme Manager with Uisce Éireann, said: "We are progressing well towards delivering this important project on behalf of the local community in the beautiful coastal village of Castletownshend.
"The new Castle pumping station is installed and ready for commissioning along with the installation of pipeline from the station to the new wastewater treatment plant. The works at the wastewater treatment plant are also well underway along with other elements of the project.
"This significant investment will boost Castletownshend by enhancing the local environment and improving water quality for swimming, rowing, and sailing. Eliminating the discharge of untreated wastewater into Castlehaven Harbour will enhance the scenic views and coastal walks around Castletownshend."
The project commenced in August 2022 with construction works due to be completed later this year. Full completion of the project is scheduled for early 2024.