Contractors have been appointed to resurface 400 metres of B8 Main Street in Pomeroy.
Works begin on 22 January and are expected to be completed by 9 February 2024.
The resurfacing works will take place from the Limehill Road to Edendoit Road and during certain periods a full road closure will be in operation.
The first road closure will commence on 22 January through to 26 January.
The second road closure will begin on 5 February through to 9 February. During this week The Diamond will also be closed for a day to allow for resurfacing there also.
During these road closures a two-way signed diversionary route will be in place via the B4 from Pomeroy to Carrickmore, the B46 from Carrickmore to the A505 Barony Road, B4 Pomeroy Road, Cookstown to Pomeroy and vice versa.
From 29 January to 2 February, two-way traffic will be maintained via lane closures under traffic signal control. During this period, works will take place each day between 9.00 am and 4.30 pm with Main Street reopened to all traffic outside of these times.