Northern Ireland-based civil engineering company Dawson Wam has provided an update on its ambitious Campbeltown Old Quay Project in Scotland.
The project, for client Argyll and Bute Council, entails the installation of a new sheet piled quay wall and dredging works.
Thus far, Dawson Wam's project team has successfully installed a new line of AZ piles, which will form the new quay wall, using one of their TM22 ABI Leader rigs.
By utilising their in-house Steel Mats as temporary works, the team were able to install the piles from the existing quay reducing the requirement for floating plant.
Dawson Wam will now be moving on to anchor installation as the next stage for the project.