Pond Park Road East To Close For Urgent Water Main Upgrade

Construction News Image

NI Water has confirmed that Pond Park Road East in Lisburn will close at the start of July for as long as six weeks to enable an urgent upgrade of the local water supply network.

Setting out the plan and traffic arrangements, Senior NI Water Project Manager, Gary McFadden, said: "The watermain on Pond Park Road East, between Aghalislone Water Pumping Station and Boomers Hill Service Reservoir, has experienced a number of bursts in recent years which have interrupted supply for many customers in the Lisburn area.

"Inspections show that a section of 660m of the existing pipeline has deteriorated and urgently needs replaced. A new larger diameter watermain – to accommodate future demand – will be laid alongside the existing main, which will remain in service while work is ongoing.

"NI Water and our project team from McAdam and GRAHAM Construction have been liaising with DfI Roads on the timing of works and will undertake the essential upgrade during the summer months in a bid to minimise traffic disruption.

-- Advertisement --

"To ensure the safety of construction workers and the public during these works, Pond Park Road East will be closed to through traffic between its junction with Lady Wallace Avenue and Mullaghglass Road from Wednesday 1st July for up to six weeks. Bus stops located within the closure area will be suspended during this time.

"GRAHAM's actual working area will be located between Old Park Road and the junction of Pond Park Road/Pond Park Road East. Access to business and residential properties on Pond Park Road East will be available from either side of the closure and a signed diversion route will be in place via Glenavy Road and Sheepwalk Road.

"We are aware that in addition to business and residential properties being located on Pond Park Road East, the road is the main route from Lisburn to Belfast International Airport. In this respect we have been engaging early with local stakeholders and extensive signage will be in place to direct motorists. We are also liaising with NIE to coordinate an upgrade to the local electricity network under the same road closure to avoid further traffic disruption in the area.

"The replacement of this watermain is a high priority for NI Water and our contractor GRAHAM will make every effort – including working extended hours and restricting July holidays to just one day – to complete the work on Pond Park Road East in the shortest possible timeframe. Final connections on Old Park Road and Pond Park Road will be carried out once Pond Park Road East has been fully reopened.

"Once complete the upgrade will improve the robustness and resilience of the local water supply network. This will be particularly important during periods of increased water demand and other emergency situations to ensure continuity of supply for our customers.

"In advance of work getting underway, the NI Water project team would like to thank local businesses, residents and the wider public for their patience and cooperation while we complete these essential water network improvements."

Latest Construction News

12/06/2026
The Minister of State for International Development and Diaspora, Neale Richmond TD, has announced a €500,000 grant to support the development of the Lancashire GAA Centre of Excellence at Broughton Park in Manchester. The Gaelic Athletic Association (GAA), Manchester City Council, and Broughton Pa
Read More
12/06/2026
SSE has secured a site at Rhode Green Energy Park in County Offaly to build a new operations base that will support the nearby 101MW Yellow River Wind Farm. The development follows the formal signing of a site agreement at Áras an Chontae in Tullamore by representatives from SSE, Offaly County Coun
Read More
12/06/2026
NI Water is continuing to advance its multi-million-pound 'Stormwater Separation Programme', an initiative designed to mitigate the risk of out-of-sewer flooding, enhance environmental performance, and unlock critical capacity within the wastewater network to facilitate new housing and economic deve
Read More
12/06/2026
FP McCann Roofing welcomed customers, colleagues, industry partners and friends to The Belfry for The Grandiose, a purpose-built golf day designed to feel different and to underline the company's commitment to long-term partnerships. Positioned as more than a routine corporate fixture, the event se
Read More
12/06/2026
Murphy's Plant team has been named Sustainability World Ambassadors at the International CSR Excellence & Green World Ambassador Awards. The programme, run by The Green Organisation, celebrates companies that use their influence to support colleagues, communities, customers, the environment and thos
Read More
12/06/2026
Northern Ireland-headquartered modular construction specialist McAvoy, in partnership with the Bradford District Care NHS Foundation Trust, has reached a key milestone with a groundbreaking ceremony marking the start of phase two of the £65 million Lynfield Mount Hospital redevelopment. McAvoy is d
Read More
12/06/2026
Uisce Éireann will install a new treated water reservoir at Kilmurray Water Treatment Plant and lay an extra 5km water main to Ballivor, boosting capacity, quality and resilience for around 2,500 customers, with works due to finish in the first half of 2027. Works are due to start next week in Ball
Read More
12/06/2026
Uisce Éireann has reached a major milestone in its multi-million-euro programme to reinforce Clonmel's water network, completing 15km of new water mains that link the Monroe water treatment plant with the Giant's Grave reservoir. With this key section finished, teams will step back from town roads
Read More
11/06/2026
Uisce Éireann is scheduled to start construction works next week in Ballivor, Co Meath, to expand storage capacity and upgrade the local water network, providing a more resilient and secure water supply for local businesses and residents. The simultaneous upgrades will be delivered across two disti
Read More
11/06/2026
GRAHAM has broken ground on a £76.8m regeneration project in Wolverton, Milton Keynes, transforming the former Agora market site into a new residential and community-focused neighbourhood. Delivered in partnership with Milton Keynes City Council and urban developer TOWN, the development will provid
Read More
WTH SuppliesConstruction Information ServicesSeamless Aluminium GroupEnviroflow Drain Cleaning and Environmental ServicesAtbec LimitedSouthern Crusher Spares LtdIndustry Training ServicesShannonside GalvanizingIrish Fencing ServicesGroundforce Ireland