Subscribe to our Construction Newsfeed
Ireland Construction Directory
Search our 25,507 companies....

Construction News

11/09/2008

Speedy Steel For 'New City' Retail Park

Structural steel firm AMSE Ltd. erected an average of 1,000 tonnes of steel per month at the €80m Abbeylands shopping complex in Ferrybank, County Waterford, it has been revealed.

This project is transforming a seven-acre site into a major shopping attraction in the region with subsequent plans having been announced to develop Ferrybank into a new Irish city

Engineering Director at AMSE, Denis McNelis, explained the fast-track nature of the scheme.

"We were appointed to the project in early 2007 and contracted to detail, fabricate and erect the primary structural steelwork. The structure is a 5 storey beam and column frame, with wide-slab pre-cast concrete floors, and a complex curved Kalzip roof. AMSE were also contracted to provide 1hour fire protection using intumescent paint, with a sealer coat on the basement car park and around the floor perimeters."

"A procurement model was quickly produced by AMSE technicians to allow 5,500 tonnes of steel to be ordered from Corus Mills rollings before the March deadline. This was achieved as AMSE engineers worked in close co-operation with Michael Punch and Partners during this critical stage of the project, to assist in bottoming out the final design."

"This partnership approach allowed 3D procurement models to be drawn in time to meet the extremely tight material procurement window. At the same time, AMSE's operations team liaised with main contractors John Paul Construction throughout February and March to agree sequencing schedules," he added.

-- Advertisement --

"In terms of tonnage this project represents the largest that AMSE has undertaken to date. We utilized 5 of our 10 site crews on this project to meet the accelerated programme. We began erecting on the 9th May and met our completion date in November," Denis explained.

Fabrication commenced at AMSE's production facility in Moate in early April and the first load was delivered to site on the first week in May. In order to satisfy an ambitious accelerated programme, within a confined site due to the phasing of other trades, the structure needed to be planned, fabricated, delivered to site and erected in a carefully planned and choreographed sequence. Foundations, concrete stairwells, lift shafts and 2 storey deep perimeter retaining walls were being constructed concurrently with the steel erection, which determined which areas of the site were available for erection.

This required that the erection of the beam and column structure was divided into 15 phases, and the erection of the roof structure into 4 phases. AMSE erection crews, under the supervision of AMSE contracts manager Rory Harris, erected four levels of steel at a time, using mobile cranes and MEWPs. The roof had to be erected using three site tower cranes as access for mobile cranes was no longer possible.

"Once 4 storeys of steel had been erected for one phase, the pre-cast slabs were lifted into place by tower crane (one of 5 JPC tower cranes on site), as the erection of steel for the next phase began," explained Rory. "By the time phase 10 steel was being erected in late August, the roof of phase 1 was already underway. Close co-ordination between AMSE and JPC on a daily basis, ensured efficient sequencing of erection throughout the project, and optimum programme delivery."

The works increased to include a further 600 tonnes of link-bridge steelwork, which only received planning permission mid-August. With no extension to the original deadline available, AMSE and Corus needed to adapt to meet the additional requirements. AMSE Purchasing Manager Anne Corcoran co-ordinated the procurement of steel from Corus Service Centres Ireland and ensured that all hot-rolled sections were delivered to AMSE's production facility on time, Efficiency and flexibilty allowed AMSE to accommodate the increased scope of works and still meet the original fabrication and erection deadlines.

Latest Construction News

17/07/2026
Cork County Council has allocated almost €200,000 in grant funding to property and business owners across the county to support improvements to town centre properties. A total of 145 applications were submitted under the 2026 Streetscape Enhancement Scheme, with funding of €199,208.85 awarded to 11
Read More
17/07/2026
MRP has secured planning permission for a £250m redevelopment of Liberty House at Kensington Olympia, following approval by the London Borough of Hammersmith & Fulham’s Planning Committee. The project will deliver 110,000 sq ft of Grade A office space and a four-star, 371-bedroom Maldron hotel, pr
Read More
17/07/2026
Dublin City Council has marked a key milestone in the regeneration of Phase 1 at Cromcastle Court and the Old Coalyard site in Coolock, Dublin 5, with the official start of demolition works. Lord Mayor of Dublin Daryl Barron officiated at the event, which signals the beginning of on-site activity t
Read More
17/07/2026
Water supplies are returning to customers in Cavan Town after a major leak on a water main at Billis Reservoir caused outages and reduced pressure on Wednesday evening. Uisce Éireann crews successfully isolated the leak and completed repair works on Thursday morning. Reservoir levels are now recove
Read More
17/07/2026
If you've just had building work done, here's the honest answer: "the builders cleaned up" and "the space is actually ready to use" are two completely different things. Most disappointment with after builders cleaning comes down to not knowing what should be included — so here's what a proper job ac
Read More
17/07/2026
Minister for Housing, Local Government and Heritage, James Browne TD, alongside Minister of State for Local Government and Planning, John Cummins TD, and Minister of State for Older People and Housing, Kieran O'Donnell TD, has published the Mid-Year Progress Report 2026 on the implementation of the
Read More
17/07/2026
Infrastructure Minister Liz Kimmins has announced a carriageway resurfacing project on the A2 Ballywalter Road in Millisle, beginning Monday 27 July 2026. The works will cover 1.1 kilometres of asphalt resurfacing from Drumfad Road to a point beyond Ballywiskin Road, aimed at improving the road’s d
Read More
17/07/2026
Swatragh-based digital construction start-up Hillside Designs is gearing up for significant expansion as it approaches its first year in business. Founded by Fintan O'Kane with support from the government-backed Go Succeed business support service, the company was established to meet growing demand
Read More
17/07/2026
Infrastructure Minister Liz Kimmins has confirmed a £420,000 carriageway resurfacing project on the A6 Glenshane Road at Curran will get under way on Monday 27 July. The scheme will cover around 1km of road between the Knockloughrim Link Road and Lurganagoose Road junctions. Minister Kimmins said:
Read More
17/07/2026
Infrastructure Minister Liz Kimmins has announced a £450,000 carriageway resurfacing scheme on the B7 Chapel Hill Road in Mayobridge, beginning on Monday 27 July 2026. The project will cover 1.6 kilometres across two stretches: an urban section from the roundabout to just beyond Chapel Car Park, an
Read More
WTH SuppliesConstruction Information ServicesShanette ShedsSLG Traffic ManagementO&O ConservatoriesSwords Auto [Traffic Management]Smart Heating Renewable SolutionsRFC SecurityIreland T&T LtdRK Enviro